ОАО “Gazprom” approves list of equipment to be manufactured on an advance financing basis
26.09.2007
ОАО “Gazprom” has approved the list of equipment with long production time to be manufactured on an advance financing basis
Equipment |
Production time |
Petrochemical equipment, pipeline valves and fittings, manufacturing equipment | |
Gas pumping units |
9-15 months |
New gas turbine engines for aircraft and vessels |
6-9 months |
Overhaul of aircraft and vessel gas turbine engines of up to 16 MW |
6 months |
Overhaul of aircraft and vessel gas turbine engines of more than 16 MW |
9-12 months |
Turboexpander units |
12 months |
Injectors |
7-12 months |
Heat recovery units |
6 months |
Dust collecting blocks |
180-360 days |
Separator blocks |
180-360 days |
Gas separator blocks |
180-360 days |
Heat exchanger blocks |
180-360 days |
Pump blocks |
180-360 days |
Tank blocks |
180-360 days |
Topping units |
180-360 days |
Column equipment |
180-360 days |
Gas air coolers |
180-360 days |
Modular automatic gas distribution stations and components |
180 days |
Pulse gas treatment uits |
180 days |
Thermal waste utilization units |
180-210 days |
Ball valves, DN 700-1400 |
180 days |
Customized ball valves with enhanced pressure integrity |
180 days |
Ball valves, “normally open” and “normally closed” actuator |
180 days |
Ball valves with electric hydraulic actuator |
180 days |
Valves DKD |
180 days |
Cocks Cameron |
300 days |
Cocks Orbit |
360 days |
Nitrogen-oxygen stations, capacity of more than 1000 cubic meters per hour |
180-210 days |
Air compression units 4GX2; 2GM2.5. |
180-360 days |
Pumping units, motor power of more than 50 kW |
180-210 days |
Gantry cranes |
более 360 days |
Electroinsulating seals (import) DN 57mm – 1420mm. |
180-230 days |
Electric equipment, automatic information management systems, instrumentation, communication equipment | |
Automatic control systems |
180 days |
Software and hardware for automatic process control systems |
180-210 days |
Software and hardware for automatic power supply control systems |
210 days |
Software and hardware for information management systems |
180 days |
Software and hardware for automatic dispatch control systems |
180 days |
Gas metering stations, automatic equipment, peripheral controllers, block-boxes (ОАО “Gazavtomatika”) |
180-200 days |
Gas and liquid metering units |
180-200 days |
Flowmeters MassProBar, ProRoc-M (manufactured by Emerson, USA). |
180-200 days |
Smart pressure sensors, proportional pressure regulators, converters (import) |
180-200 days |
Integrated security systems |
180-200 days |
Waste gas analyzer, dewmeters, level gages, in-line chromatographs (manufactured by Klacis A Poten, Daniel, Artvik, Anstromet, etc.) |
180-200! days |
Vibration control systems (import) |
180-200 days |
Calibration rig for calibration testing of mass flow meters Compact Prover (manufactured by OOO “Ways Alfa”, etc.) |
200-220 days |
Laboratory equipment (fixed gas analyzers, chromatographs) (import) |
180-200 days |
Electric power plants (500 KW and more); |
180 days |
Gas turbine drives |
from 180 days |
Electric gas pumping units |
350 days |
Complete distribution devices (customized) |
from 180 days |
Complete transformer substations (customized) |
from 180 days |
High power electric motors of 1000 KW and more (made to configuration data sheets) |
from 180 days |
Variable frequency drives (made to configuration data sheets) |
from 180 days |
Block and unit devices (made to configuration data sheets) |
from 180 days |
Power units (customized) |
from 180 days |
High voltage circuit breakers (gas-insulated) |
from 180 days |
Transformers, power of more than 1000 KW |
from 180 days |
Trunking communication systems |
210 days |
Teleautomatic equipment |
240 days |
Radio relay systems |
185 days |
Digital telecommunication equipment |
185 days |
Gas field equipment, drilling equipment and special-purpose machinery | |
Tractors and road-construction equipment, load capacity of more than 50 tons (import) |
up to 240 days |
Buses (import) |
up to 240 days |
Exploration and production drilling rigs, workover rigs |
up to 360 days |
Christmas trees (cathodic protection) |
up to 240 days |
Well cluster control systems |
up to 240 days |
Pumping units for hydraulic fracture |
up to 200 days |
Blowout preventors |
up to 300 д! ней |
Downhole equipment |
up to 270 days |
Mud pumps |
up to 250 days |
Wellhead equipment |
up to 300 days |
Spares for various import equipment |
up to 250 days |
Spares for fixed gas pumping units GTN-6, GT-6-750, GTN-25-1, GTK-10-4, KOU GTK-10-4, GTK-5, GTN-25/76, GT-750-6(5), drives, injectors, GTK-10I(10IR), GTN-25I(25IR), PZhT-10(21S), Taurus 60S, GTNR-16, Centaur, Cobbera, Solar, injectors
|
up to 240 days |
Spares for gas pumping units with vessel engines for GPU -10, GPU-1 6, GPA-16MZh (16G), injectors, engines |
up to 240 days |
Spares for gas pumping units with aircraft engines for GPA-C-16 (6,3), GPA-C-8 (18), GPA-16 GPA-C-25, GPA-12, injectors, engines |
up to 240 days |
Spares for electric drives of gas pumping equipment for STD-4000, STD-12500, SDG-12500, EGPA-C-6,3 (6,3К), АZ-4500, EGPA-25RCh, injectors |
up to 240 days |
Spares for gas compressors MK-8, 10 GKN, DG-12 |
up to 240 days |
Static frequency converters |
up to 240 days |
Regenerators, air heaters for gas pumping units |
up to 240 days |
Large diameter pipes, oilfield tubular goods | |
Pipes, DN 530-1420 (import) |
180-360 days |
Threaded oilfield tubular goods (pump and compressor tubes, imported casings) |
180-360 days |