Equipment |
Production time |
Petrochemical equipment, pipeline valves and fittings, manufacturing equipment | |
Gas pumping units |
9-15 months |
New gas turbine engines for aircraft and vessels |
6-9 months |
Overhaul of aircraft and vessel gas turbine engines of up to 16 MW |
6 months |
Overhaul of aircraft and vessel gas turbine engines of more than 16 MW |
9-12 months |
Turboexpander units |
12 months |
Injectors |
7-12 months |
Heat recovery units |
6 months |
Dust collecting blocks |
180-360 days |
Separator blocks |
180-360 days |
Gas separator blocks |
180-360 days |
Heat exchanger blocks |
180-360 days |
Pump blocks |
180-360 days |
Tank blocks |
180-360 days |
Topping units |
180-360 days |
Column equipment |
180-360 days |
Gas air coolers |
180-360 days |
Modular automatic gas distribution stations and components |
180 days |
Pulse gas treatment uits |
180 days |
Thermal waste utilization units |
180-210 days |
Ball valves, DN 700-1400 |
180 days |
Customized ball valves with enhanced pressure integrity |
180 days |
Ball valves, “normally open” and “normally closed” actuator |
180 days |
Ball valves with electric hydraulic actuator |
180 days |
Valves DKD |
180 days |
Cocks Cameron |
300 days |
Cocks Orbit |
360 days |
Nitrogen-oxygen stations, capacity of more than 1000 cubic meters per hour |
180-210 days |
Air compression units 4GX2; 2GM2.5. |
180-360 days |
Pumping units, motor power of more than 50 kW |
180-210 days |
Gantry cranes |
более 360 days |
Electroinsulating seals (import) DN 57mm – 1420mm. |
180-230 days |
Electric equipment, automatic information management systems, instrumentation, communication equipment | |
Automatic control systems |
180 days |
Software and hardware for automatic process control systems |
180-210 days |
Software and hardware for automatic power supply control systems |
210 days |
Software and hardware for information management systems |
180 days |
Software and hardware for automatic dispatch control systems |
180 days |
Gas metering stations, automatic equipment, peripheral controllers, block-boxes (ОАО “Gazavtomatika”) |
180-200 days |
Gas and liquid metering units |
180-200 days |
Flowmeters MassProBar, ProRoc-M (manufactured by Emerson, USA). |
180-200 days |
Smart pressure sensors, proportional pressure regulators, converters (import) |
180-200 days |
Integrated security systems |
180-200 days |
Waste gas analyzer, dewmeters, level gages, in-line chromatographs (manufactured by Klacis A Poten, Daniel, Artvik, Anstromet, etc.) |
180-200! days |
Vibration control systems (import) |
180-200 days |
Calibration rig for calibration testing of mass flow meters Compact Prover (manufactured by OOO “Ways Alfa”, etc.) |
200-220 days |
Laboratory equipment (fixed gas analyzers, chromatographs) (import) |
180-200 days |
Electric power plants (500 KW and more); |
180 days |
Gas turbine drives |
from 180 days |
Electric gas pumping units |
350 days |
Complete distribution devices (customized) |
from 180 days |
Complete transformer substations (customized) |
from 180 days |
High power electric motors of 1000 KW and more (made to configuration data sheets) |
from 180 days |
Variable frequency drives (made to configuration data sheets) |
from 180 days |
Block and unit devices (made to configuration data sheets) |
from 180 days |
Power units (customized) |
from 180 days |
High voltage circuit breakers (gas-insulated) |
from 180 days |
Transformers, power of more than 1000 KW |
from 180 days |
Trunking communication systems |
210 days |
Teleautomatic equipment |
240 days |
Radio relay systems |
185 days |
Digital telecommunication equipment |
185 days |
Gas field equipment, drilling equipment and special-purpose machinery | |
Tractors and road-construction equipment, load capacity of more than 50 tons (import) |
up to 240 days |
Buses (import) |
up to 240 days |
Exploration and production drilling rigs, workover rigs |
up to 360 days |
Christmas trees (cathodic protection) |
up to 240 days |
Well cluster control systems |
up to 240 days |
Pumping units for hydraulic fracture |
up to 200 days |
Blowout preventors |
up to 300 д! ней |
Downhole equipment |
up to 270 days |
Mud pumps |
up to 250 days |
Wellhead equipment |
up to 300 days |
Spares for various import equipment |
up to 250 days |
Spares for fixed gas pumping units GTN-6, GT-6-750, GTN-25-1, GTK-10-4, KOU GTK-10-4, GTK-5, GTN-25/76, GT-750-6(5), drives, injectors, GTK-10I(10IR), GTN-25I(25IR), PZhT-10(21S), Taurus 60S, GTNR-16, Centaur, Cobbera, Solar, injectors
|
up to 240 days |
Spares for gas pumping units with vessel engines for GPU -10, GPU-1 6, GPA-16MZh (16G), injectors, engines |
up to 240 days |
Spares for gas pumping units with aircraft engines for GPA-C-16 (6,3), GPA-C-8 (18), GPA-16 GPA-C-25, GPA-12, injectors, engines |
up to 240 days |
Spares for electric drives of gas pumping equipment for STD-4000, STD-12500, SDG-12500, EGPA-C-6,3 (6,3К), АZ-4500, EGPA-25RCh, injectors |
up to 240 days |
Spares for gas compressors MK-8, 10 GKN, DG-12 |
up to 240 days |
Static frequency converters |
up to 240 days |
Regenerators, air heaters for gas pumping units |
up to 240 days |
Large diameter pipes, oilfield tubular goods | |
Pipes, DN 530-1420 (import) |
180-360 days |
Threaded oilfield tubular goods (pump and compressor tubes, imported casings) |
180-360 days |