ОАО “Gazprom” has approved the list of equipment  with long production time to be manufactured on an advance financing basis

 
Equipment
Production time
Petrochemical equipment, pipeline valves and fittings, manufacturing equipment 
Gas pumping units
9-15 months
New gas turbine engines for aircraft and vessels 
6-9 months
Overhaul of aircraft and vessel gas turbine engines of up to 16 MW
6 months
Overhaul of aircraft and vessel gas turbine engines of more than 16 MW
9-12 months
Turboexpander units
12 months
Injectors
7-12 months
Heat recovery units
6 months
Dust collecting blocks
180-360 days
Separator blocks
180-360 days
Gas separator blocks
180-360 days
Heat exchanger blocks
180-360 days
Pump blocks
180-360 days
Tank blocks
180-360 days
Topping units
180-360 days
Column equipment
180-360 days
Gas air coolers
180-360 days
Modular automatic gas distribution stations and components
180 days
Pulse gas treatment uits
180 days
Thermal waste utilization units 
180-210 days
Ball valves,  DN 700-1400
180 days
Customized ball valves  with enhanced pressure integrity
180 days
Ball valves,  “normally open” and “normally closed”
 actuator   
180 days
Ball valves with electric hydraulic actuator 
180 days
Valves DKD
180 days
Cocks Cameron
300 days
Cocks  Orbit
360 days
Nitrogen-oxygen stations, capacity of more than 1000 cubic meters per hour 
180-210 days
Air compression units  4GX2; 2GM2.5.
180-360 days
Pumping units, motor power of more than 50 kW
180-210 days
Gantry cranes
более 360 days
Electroinsulating seals (import) DN 57mm – 1420mm.
180-230 days
Electric equipment, automatic information management systems, instrumentation, communication equipment 
Automatic control systems
180 days
Software and hardware for automatic process control systems
180-210 days
Software and hardware for automatic power supply control systems
210 days
Software and hardware for information management systems  
180 days
Software and hardware  for automatic dispatch control systems
180 days
Gas metering stations, automatic equipment, peripheral controllers, block-boxes (ОАО “Gazavtomatika”)
180-200 days
Gas and liquid metering units 
180-200 days
Flowmeters  MassProBar, ProRoc-M (manufactured by  Emerson, USA).
180-200 days
Smart pressure sensors, proportional pressure regulators, converters  (import)
180-200 days
Integrated security systems
180-200 days
Waste gas analyzer, dewmeters, level gages, in-line chromatographs  (manufactured by Klacis A Poten, Daniel, Artvik, Anstromet, etc.)
180-200! days
Vibration control systems  (import)
180-200 days
Calibration rig for  calibration testing of mass flow meters  Compact Prover (manufactured by OOO “Ways Alfa”, etc.)
200-220 days
Laboratory equipment  (fixed gas analyzers, chromatographs)  (import)
180-200 days
Electric power plants (500 KW and more);
180 days
Gas turbine drives
from 180 days
Electric gas pumping units
350 days
Complete  distribution devices (customized) 
from 180 days
Complete transformer substations (customized)
from 180 days
High power electric motors of 1000 KW and more (made to configuration data sheets)
from 180 days
Variable frequency drives  (made to configuration data sheets)
from 180 days
Block and unit devices (made to configuration data sheets)
from 180 days
Power units (customized)
from 180 days
High voltage circuit breakers  (gas-insulated)
from 180 days
Transformers, power of more than 1000 KW
from 180 days
Trunking communication systems
210 days
Teleautomatic equipment
240 days
Radio relay systems
185 days
Digital telecommunication equipment
185 days
Gas field equipment, drilling equipment and special-purpose machinery 
Tractors and road-construction equipment, load capacity of more than 50 tons (import)   
up to  240 days
Buses (import)
up to  240 days
Exploration and production drilling rigs, workover rigs
up to  360 days
Christmas trees (cathodic protection)
up to  240 days
Well cluster control systems
up to  240 days
Pumping units for hydraulic fracture 
up to  200 days
Blowout preventors
up to  300 д! ней
Downhole equipment
up to  270 days
Mud pumps
up to  250 days
Wellhead equipment
up to  300 days
Spares for various import equipment
up to  250 days
Spares for fixed gas pumping units  GTN-6, GT-6-750, GTN-25-1, GTK-10-4, KOU GTK-10-4, GTK-5, GTN-25/76, GT-750-6(5), drives, injectors, GTK-10I(10IR), GTN-25I(25IR), PZhT-10(21S), Taurus 60S, GTNR-16, Centaur, Cobbera, Solar, injectors 
 
up to  240 days
Spares for gas pumping units with vessel engines for GPU -10, GPU-1 6, GPA-16MZh (16G), injectors, engines
up to  240 days
Spares for gas pumping units with aircraft engines for GPA-C-16 (6,3), GPA-C-8 (18), GPA-16 GPA-C-25, GPA-12, injectors, engines
up to  240 days
Spares for electric drives of gas pumping equipment for STD-4000, STD-12500, SDG-12500, EGPA-C-6,3 (6,3К), АZ-4500, EGPA-25RCh, injectors 
up to  240 days
Spares for gas compressors MK-8, 10 GKN, DG-12
up to  240 days
Static frequency converters
up to  240 days
Regenerators, air heaters for gas pumping units
up to  240 days
Large diameter pipes,  oilfield tubular goods
Pipes, DN 530-1420 (import) 
180-360 days
Threaded oilfield tubular goods  (pump and compressor tubes, imported casings)