More than 70 million rubles will be allocated by Khabarovsk Generation for the repair and modernization of the CHPP-1 turbine
19.07.2019
Power engineers of Khabarovsk CHPP-1 (branch "Khabarovsk generation" of JSC "DGK") brought turbine unit No. 8 into medium repair. 117 days are planned for the production of works. The renovation will be completed in the last ten days of October.
The turbine will have to open low, medium and high pressure cylinders, metal inspection, replacement of the stop valve and cylinder fasteners, replacement of high and low pressure rotor stage blades, replacement of stage diaphragms of the medium cylinder pressure.
"Modernization and timely repair of power plant equipment allows to extend its service life", - comments the director of Khabarovsk generation Vladimir Larikov.
Khabarovsk Generation plans to allocate 70.5 million rubles for the repair and modernization of turbine No. 8. This is one of the most significant stages of the Khabarovsk CHPP-1 repair program for the current season. As part of this program, generator No. 6 has already been overhauled, and a major overhaul of boiler No. 7 is planned, as well as a number of ongoing repairs.