Energy Modernization in Russia: RusHydro Increases Production Capacities
23.01.2025

The most significant project was the re-equipment of the Ezminskaya power plant. Here, engineers completely replaced the power equipment of three units. A major overhaul of all hydraulic structures was carried out. The work carried out allowed to increase the capacity of the facility by 15 MW.
Significant improvements were also made at other stations. The Nizhny Novgorod hydroelectric complex received an additional 7.5 MW. The Saratov station increased its capacity by 6 MW. The Votkinsk power facility added 5 MW. A modern turbine and generator stator were installed at the Cheboksary hydroelectric power station.
Active work is underway at the Chirkeyskaya, Sengileyevskaya stations and the Kuban pumped storage power station. Installation of a new unit has begun at the Uglich hydroelectric power station. Builders are constructing distribution complexes at the Volzhskaya Hydroelectric Power Station and three stations of the Kuban Cascade.
Over the 12-year period of modernization, energy capacity has increased by 631.5 MW. Specialists have installed 145 new turbines, 153 generators, and 108 transformers. Over 10 thousand units of auxiliary systems have been replaced.
Technical re-equipment affects all key units of the stations. The plan provides for the renewal of 50% of the main equipment. Particular attention is paid to the reliability of hydraulic structures.
The modernization program will continue in 2025. The introduction of innovative technologies will significantly increase the efficiency of the country's energy system. The new equipment has improved characteristics and a long service life.
The implementation of the technical upgrade project is of strategic importance. It ensures Russia's energy security and creates a foundation for further development of the industry.The use of modern technologies reduces operating costs and increases the reliability of energy supply.
Representatives of the company "RusHydro" are invited to the VII Conference "Investment projects, modernization, procurement in the electric power industry", Investenergo-2025, which will be held on February 27, 2025 at the Hotel Continental